PROJECT MANAGEMENT

Zuccoli South SPS

Description

Delivery of critical sewer infrastructure servicing Stages 3 and 4 of Zuccoli Aspire, including the new southern sewer pump station and approximately 600 metres of rising main connected into the wider trunk sewer network.

The project required close coordination with Power and Water Corporation to secure approvals, manage staging and deliver capacity for both current development and future adjoining catchments.

Details

Project
Zuccoli South SPS

Project Date
2016 – 2017

Client
Costojic Pty Ltd

Sector
Civil Infrastructure / Utilities

Location
Zuccoli, Palmerston

Value
$4M construction value

KEY OUTCOMES

  • Delivered critical trunk sewer infrastructure enabling future stages
  • Secured servicing capacity for 1,871 equivalent population
  • Integrated future Mitchell catchment servicing requirements
  • Coordinated authority approvals and staged infrastructure delivery
  • Supported broader Zuccoli Aspire masterplan rollout

OUR ROLE

  • Development management
  • Project management
  • Authority coordination
  • Consultant coordination
  • Infrastructure delivery oversight
  • Contract administration support